Sinkhole fix nearly complete

Sinkhole fix nearly complete

The Mount Gambier City Council is finalising remediation work at the sinkhole in the walkway between Margaret Street and the Railway Lands, with public thoroughfare access to be reopened next week.


Collapsing bitumen revealed the cavity following heavy rain in June 2023.


Council’s Acting General Manager City Infrastructure Karl Manarangi said an independent geotechnical investigation was undertaken by engineering consultants which recommended filling the 30 square metre void.


“We have been monitoring the site for movement in the sinkhole after remedial works were undertaken last month, and there has been no movement to date,” he said.


“Therefore, the walkway will be accessible to the public once again early next week and the toilets will also be reopened.


“We are still awaiting a contractor to apply the final layer of asphalt to reseal the top of the sinkhole. This should occur within the next eight weeks and the site may be closed for a day to enable this work to occur.


“The area around the sinkhole will remain fenced off until the resealing works are complete, however the walkway will still be accessible.”

Why wait? Get more stories like this delivered straight to your inbox
Join our digital edition mailing list and stay up to date on the latest news, events and special announcements from across the Limestone Coast.

Your local real estate guide - every Thursday

spot_img

You might also like